Shorts aur news mein “ISRO ka naya launch pad” ghoom raha hai, aur comments mein ek hi sawaal baar-baar: “Sriharikota mein pehle se do pad hain, teesra kis liye? Aur Tamil Nadu mein alag spaceport kyun?” Lagta hai jaise ek ghar mein teesra gate lagaya ja raha ho. Asal kahani gate ki nahi, ghadi ki hai.
โก Seedha jawab
Union Cabinet ne 16 Jan 2025 ko Sriharikota mein Third Launch Pad (TLP) manzoor kiya: โน3,984.86 crore, 48 mahine. Kaam: naye bade rocket NGLV (30 tonne tak low Earth orbit) ke liye pad, Second Launch Pad ka standby, aur insaani udaan ke liye zyada capacity. ISRO chief ke mutabik 2029 tak India ke paas 4 launch pad honge.
Source: ISRO/PIB Cabinet note 16 Jan 2025; News On AIR 26 Oct 2026
Last verified: 24 November 2026. 22โ23 Nov 2026 ko kisi naye pad ka udghatan ya nayi ghoshna hamein official source mein nahi mili; ye post 4-pad plan ko samjhaati hai.
Launch pad asal mein karta kya hai?
๐ง Samjho aise: ek hi platform wala station
Ek station socho jahan lambi Rajdhani sirf ek platform par lag sakti hai. Wahan safai ya marammat chal rahi ho, to baaki saari lambi trainein rukti hain, chahe patriyan aur engine sab taiyaar hon.
Rocket ke liye wo platform hai launch pad: wo jagah jahan rocket khada hota hai, fuel bhara jaata hai, aakhri jaanch hoti hai aur ulti ginti chalti hai. Bade rocket ke liye India ke paas abhi aisa ek hi “lamba platform” hai: Second Launch Pad.
Ek line jo sab badal deti hai: launch pad jagah nahi, ek ghadi hai. Rocket jitni der pad par khada, utni der agla rocket intezaar karta hai.
Rocket pad par kaise taiyaar hota hai? 2 tareeke

- Integrate on Pad (First Launch Pad): ISRO ke mutabik FLP 1990s ki shuruaat mein bana. Yahan rocket ke hisse pad par hi, lagbhag 3,200 ton ke Mobile Service Tower ke andar ek-ek karke jode jaate hain. Jab tak rocket jud raha hai, pad usi ka hai.
- Integrate, Transfer, Launch (Second Launch Pad, 2005 se): rocket alag building mein khada-khada joda jaata hai, phir rail par pad tak le jaaya jaata hai. Pad kam samay ghirta hai, isliye wahi pad zyada launch sambhaal sakta hai.
- Kaunsa rocket kahan: Cabinet note ke mutabik FLP aaj bhi PSLV aur SSLV ke liye hai. SLP GSLV aur LVM3 ke liye bana, Chandrayaan-3 yahin se gaya, aur Gaganyaan ki taiyari yahin ho rahi hai.
- Dikkat: sabse bade aur insaan le jaane wale rocket sirf SLP par. Cabinet note khud kehta hai ki TLP “standby launch pad for SLP” bhi hoga, yaani abhi SLP ka koi backup nahi.
Pehle jo sahi hai: do pad se ISRO ne Chandrayaan aur Mangalyaan jaise mission kiye hain. Mudda ye nahi ki purane pad kamzor hain; mudda ye hai ki aane wale kaam unke size aur ginti se bade hain.
Teesre pad ki zaroorat kyun? Cabinet ne kya likha
- Bade rocket: NGLV (Next Generation Launch Vehicle) ka lakshya 30 tonne tak low Earth orbit. Cabinet note (18 Sep 2024) ke mutabik aaj ke Indian rocket lagbhag 10 tonne tak le jaate hain. Yaani lagbhag 3 guna.
- Bade sapne: Bharatiya Antariksh Station 2035 tak aur 2040 tak chaand par Indian astronaut. ISRO ke shabdon mein ye zarooratein “cannot be met by the existing launch pads”.
- Design: “as universal and adaptable as possible”: NGLV, semi-cryogenic stage wala LVM3 aur NGLV ke bade roop, sab ke liye. Umar: aane wale 25โ30 saal.
- Timeline: sarkar ke Parliament jawab (Aug 2025, Tribune report) ke mutabik civil kaam May 2028 tak, aur chalu March 2029 tak. Ek Lok Sabha jawab ki report (Swarajya, Mar 2026) 2029โ30 batati hai, ise ek hi source ki baat maaniye.
Ek shabd, do matlab: “naya launch pad”
Khabron mein “naya launch pad” do alag jagahon ke liye likha jaata hai, aur log dono ko ek samajh lete hain:

- Third Launch Pad, Sriharikota (Andhra Pradesh): bade rocket (NGLV), insaani udaan ka backup. Lakshya 2029.
- SSLV Launch Complex, Kulasekarapattinam (Thoothukudi, Tamil Nadu): chhote rocket SSLV aur private companiyon ke launch ke liye. PM ne 28 Feb 2024 ko neev rakhi; ISRO chief ne 5 Nov 2026 ko kaha ki agle saal (2027) wahan se rocket udega (PTI).
Tamil Nadu mein alag spaceport kyun?
ISRO ke shabd: ye jagah “direct southward launch trajectory” se chhote rocket ki payload capacity badhati hai. Iska matlab samjhiye:
- Polar orbit (jo dhruvon ke upar se ghoomti hai) ke liye rocket ko lagbhag seedha dakshin jaana hota hai.
- Officials ke hawale se media reports (Deccan Herald) ke mutabik Sriharikota se dakshin jaate rocket ko Sri Lanka ke upar se bachne ke liye pehle dakshin-poorab jaakar mudna padta hai. Mudne mein fuel jaata hai.
- Kulasekarapattinam se rasta seedha samudra ke upar dakshin hai. Chhote rocket ke liye bacha hua fuel matlab zyada payload.
Fooled-then-reveal: pehli nazar mein lagta hai “naya pad = naya rocket”. Asal mein fark disha ka hai: ek hi rocket, alag jagah se, kam ghoom kar, zyada saaman le ja sakta hai. Ye wahi baat hai jo class 9 mein padhi thi: raasta jitna seedha, kaam utna kam.
Aur Sriharikota hi kyun? ISRO ke mutabik ye equator ke paas, poorvi samudra tat par hai. General science: Dharti pashchim se poorab ghoomti hai, to poorab ki taraf jaate rocket ko kuch raftaar muft milti hai, aur equator ke paas ye boost zyada hota hai. Poorab mein khula samudra hai, to rocket ke hisse aabaadi se door girte hain.
Viral baat vs pakki baat
| Jo suna | Kya pakka hai |
|---|---|
| “Teesra launch pad ban gaya / shuru ho gaya” | Nahi. Manzoori Jan 2025, lakshya March 2029 (govt reply). 24 Nov 2026 tak chalu hone ki koi official khabar nahi. |
| “NGLV 30,000 tonne le jaayega” | Galat (typo). Cabinet note: 30 tonne tak low Earth orbit. |
| “Tamil Nadu wala pad aur teesra pad ek hi hai” | Nahi. Teesra pad Sriharikota mein (bade rocket); Kulasekarapattinam SSLV ke liye alag complex. |
| “Naya pad aate hi har mahine launch” | Abhi pata nahi. Saal mein kitne launch, iska official aankda nahi mila; ye rocket banne ki raftaar par bhi tika hai. |
Agli baar headline padhein to ye 3 sawaal
- Kaunsa pad? Sriharikota ka Third Launch Pad ya Kulasekarapattinam ka SSLV complex?
- Kis rocket ke liye? Bada NGLV/LVM3 ya chhota SSLV?
- Kaunsa padaav? Manzoori, neev, nirmaan, ya pehla launch? Har padaav mein saal ka fark hota hai.
Space ka ek aur mazedaar hisaab: Voyager 1 ek light-day door, iska matlab kya?
Ek line mein: teesra pad isliye, kyunki bade rocket aur insaani udaan ke liye abhi India ke paas sirf ek “lamba platform” hai, aur ek platform wala station kabhi bhi ruk sakta hai.
Log ye bhi poochhte hain
NGLV kya hai?
Next Generation Launch Vehicle: ISRO ka aane wala bada rocket jiska pehla stage dobara istemaal ho sakega. Cabinet ne 18 Sep 2024 ko โน8,240 crore manzoor kiye, jisme 3 development udaanein shamil hain. Lakshya 30 tonne tak low Earth orbit.
Gaganyaan kis launch pad se jaayega?
Cabinet note ke mutabik Second Launch Pad human-rated LVM3 ke liye taiyar ho raha hai. Teesra pad aage chalkar insaani udaan ke liye backup aur zyada capacity dega.
Kulasekarapattinam se pehla launch kab hoga?
ISRO chief V. Narayanan ne 5 Nov 2026 ko kaha ki agle saal (2027) wahan se rocket launch hoga. Tamil Nadu ne lagbhag 2,300 acre zameen di hai (PTI).
Ek launch pad banne mein itna samay kyun lagta hai?
Pad sirf platform nahi: fuel ke tank aur pipeline, tower, jaanch ke system, suraksha ke intezaam sab saath banate hain. Cabinet ne TLP ke liye 48 mahine rakhe hain.
Source
- ISRO, 16 Jan 2025: Cabinet approves Third Launch Pad (โน3,984.86 cr, 48 mahine, uddeshya, design)
- PM India, 18 Sep 2024: Cabinet approves NGLV (30 t LEO, โน8,240 cr)
- ISRO: Launch services, SDSC SHAR (FLP, SLP, Mobile Service Tower, location)
- News On AIR, 26 Oct 2026: four functional launch pads by 2029
- Tribune, Aug 2025: govt reply, TLP operational by March 2029
- ISRO, 28 Feb 2024: foundation stone, second spaceport (southward trajectory)
- ISRO, Aug 2025: foundation stone for launch pad at SSLV Launch Complex
- ThePrint (PTI), 5 Nov 2026: launches from Kulasekarapattinam next year
- Deccan Herald, 2022: second launch pad in Tamil Nadu (Sri Lanka route, officials)
- Swarajya, Mar 2026: Lok Sabha reply on timelines (single source)
Space ka kaunsa sawaal aapko hamesha uljhaata hai? Neeche likhiye.